Does your building need a TM44 inspection?

If your building's air conditioning adds up to more than 12kW, you are legally required to hold a valid TM44 report. Here's what that means in practice.

Many building owners and facilities managers don't realise their air conditioning needs a statutory energy inspection. Under the Energy Performance of Buildings Directive, every air conditioning system with a combined effective rated output of more than 12kW must have a valid TM44 inspection report.

Does the 12kW threshold apply per unit?

No – it is the combined cooling output of all the units in the building. An office with four 4kW split systems is over the threshold, even though no single unit is.

How often is an inspection needed?

At intervals not exceeding five years. In Scotland the interval can be as short as three years where systems are assessed as poorly maintained or inefficient.

Who is responsible?

The "responsible person" – usually the building owner, occupier or whoever controls the air conditioning system. Failure to produce a valid report on request can result in a fixed penalty of £300 per offence, which Trading Standards can repeat.

What does the report include?

  • An assessment of system efficiency and sizing against the cooling load
  • The maintenance condition of the equipment
  • Controls and system set-up
  • Practical no-cost and low-cost recommendations to reduce energy use and running costs

How GMA can help

GMA's assessors are qualified to carry out both Level 3 (simple split and packaged systems) and Level 4 (VRF, chillers, AHUs and other complex systems) inspections, and are accredited with Sterling Accreditation.

Find out more about our TM44 inspections or request a quote.